On the 4th of July 2016 Allnamics checked the capacity and stiffness of 4 production piles (Fundex-type), commissioned by contractor Ballast Nedam Industriebouw BV. The piles are part of the tank foundation for the UREA Granulation 8 Project on the production yard of Yara in Sluiskil, the Netherlands. Rapid Load Testing system StatRapid has been deployed, with which, following CUR guideline 230, the load-displacement behaviour of the piles has been determined.

The proof load testing was a contractual requirement and the (positive) results are regarded as representative for the entire tank foundation. Consequently the foundation slab has been cast with high confidence in the foundation design.

In case you are interested in more information on Rapid Load Testing and StatRapid, please contact us.